The Future of Line 5 in the Straits of Mackinac





Now that Michigan’s governor and attorney general have sunk the oil tunnel scheme hatched by the last administration, I’m asked nearly every day: What can citizens and state leaders do to shut down the propped-up, banged-up Line 5 oil pipelines in the Straits of Mackinac for good?

Here’s my answer, as succinctly as I can distill it, accompanied by a summary of the law and political history in play.

So what should Governor Whitmer and Attorney General Nessel do?

Governor Gretchen Whitmer and Attorney General Dana Nessel must take swift and comprehensive actions to review and reverse the improper failure of the former Snyder administration to bring Line 5-owner Enbridge under the rule of law. Enbridge has had its way with Michigan’s prior elected officials, and it is time to call a halt to this nonsense. Here are the steps to getting Enbridge out of the Great Lakes for good:

Proposed Oil Tunnel:

  1. Send a Letter: Tunnel Deal Is Dead– Governor Whitmer and Attorney General Nessel should send a formal letter to Enbridge advising the company that its agreements calling for a transfer or occupancy of the Straits of Mackinac public trust bottomlands, the new state-granted easement, and 99-year lease for the proposed oil tunnel that would house a new Line 5 are unenforceable unless Enbridge has obtained authorization under state law – the Great Lakes Submerged Lands Act (GLSLA).

Line 5 in the Straits:

  1. Send another Letter: No Life Support for Line 5 – Governor Whitmer and the Michigan Department of Environmental Quality (DEQ), along with Attorney General Nessel, should send a letter to Enbridge advising it that the agreements purporting to grant Enbridge occupancy and use of waters and bottomlands the existing Line 5 for 10 years or more are unenforceable, because the former administration and Enbridge failed to obtain the required authorization under the GLSLA.
  1. Apply the Law to the Redesign of the Ailing Pipelines – Governor Whitmer and the DEQ, along with Attorney General Nessel, should investigate and correct the lack of review and showings required by the GLSLA and public trust law for the substantial change in design implemented for the 3 miles of pipeline elevated above the lakebed under the guise of “repair.” Enbridge should be instructed that it must show the risks and magnitude of harm are minimal and that there exist no other alternative than the existing line in the Straits or Great Lakes.

How Did We Get Here on Line 5? Tracing the Law and the Politics

The plotting of former Governor Snyder’s administration and Enbridge to hand over the public trust soils and bedrock under the Straits of Mackinac for the company to build and operate a new crude oil pipeline in a tunnel for 99 years has been put on hold.

On her first full day in office, Governor Gretchen Whitmer asked Attorney General Dana Nessel for a formal opinion on whether the Snyder-Enbridge agreement and legislature’s stamp of approval through a lame-duck law known as “Act 359” to hand over the Straits for Enbridge’s tunnel  to Enbridge was constitutional.  In late March, Attorney General Nessel found it was not constitutional because the legislature tried to graft a private tunnel-pipeline project onto a public infrastructure law that governs a public icon—the Mackinac Bridge.

Read more about the history and law surrounding Line 5 here!

  1. Revoke the Easement – Attorney General Nessel along with the Department of Natural Resources (DNR), along with the above actions, revoke the 1953 easement because under the current circumstances the existing Line 5 is no longer in compliance with the common law standards of the paramount interests of the Great Lakes protected by public trust law; if Enbridge desires to continue using the existing line in the Straits, the company must submit an application for authorization of such use and occupancy along with the authorizations identified in this list.
  1. Increase Insurance Requirement and Verify It – Governor Whitmer, the DEQ, and the DNR, with the Attorney General, should require Enbridge to submit financial assurances that cover the worst case economic and natural resources damages of at least $6 billion (significantly more than the current cap of $1.8 billion), retain qualified experts to determine the adequacy of those assurances, and require Enbridge to name the State of Michigan as an “additional insured” and/or “named insured” on its insurance coverage for Line 5. Inadequate insurance is another cause for revoking the easement.

Once the Governor and Attorney General do these things, they will have taken action consistent with their pledge in being elected to lead the State and protect the Great Lakes, by nullifying the improper actions and agreements of their predecessors and bringing Enbridge, finally, under the rule of law. Regardless of the outcome, the interested parties, communities, and persons in this controversy and the government will be required to make determinations concerning the fate of Line 5 in an open forum based on facts, science, and law.  We are ruled by law, not by self-serving agreements that were plotted to avoid it.

Given President Trump’s executive orders this week to water-down or smooth over federal laws and regulations affecting water, the Great Lakes, and pipelines, it is more critical than ever that Governor Whitmer and Attorney General Nessel exercise the full jurisdiction and authority they and the State of Michigan under its exclusive power over use of the waters and bottomlands of the Great Lakes, its lakes and streams, public lands, and the public trust in the Great Lakes and navigable waters and public common property of Michigan. This trust imposes a duty on our leaders to protect the interests of citizens, the legal beneficiaries of this trust. Not the President, not Congress, not federal agencies, or state government can repeal, limit, or narrow the state’s duties and citizens’ individual and common rights under this public trust.

What Should Citizens Do?

It is quite simple: Citizens should do what they always do best. Continue to stay involved, increase communications to Governor Whitmer, Attorney General Nessel, and the Director of the DEQ, and the DNR.  These communications should do the following:

  • Thank our state leaders for taking action on the unconstitutional Act 359 and the misguided oil tunnel agreement;
  • Urge our state leaders to take immediate steps to implement the actions outlined above to formally scrap the oil tunnel and shut down Line 5.

FLOW Praises Attorney General for Restoring Rule of Law on Line 5


FOR IMMEDIATE RELEASE:                                                                      March 28, 2019

Liz Kirkwood, FLOW Executive Director                                                   Email:Liz@FLOWforWater.org
Office: (231) 944-1568, Cell: (570) 872-4956                                           Web: www.FLOWforWater.org

Jim Olson, FLOW Founder and President                                                Email:olson@envlaw.com
Cell: (231) 499-8831

Dave Dempsey, FLOW Senior Advisor                                                     Email:Dave@FLOWforWater.org
(612) 703-2720


FLOW supports attorney general’s process and opinion, which is binding on state agencies and rejects the fatally flawed law and undermines side agreements on Enbridge oil pipelines, proposed tunnel in Mackinac Straits


In a major step toward restoring the rule of law, Michigan Attorney General Dana Nessel issued an opinion today declaring unconstitutional a hastily crafted law that sought to give away Great Lakes public trust bottomlands to Enbridge for 99 years for a private oil tunnel, while allowing the aged, dangerous existing “Line 5” oil pipelines in the Straits to continue operating for another decade as the tunnel is considered and possibly built.

The move comes in response to a formal request by Gov. Gretchen Whitmer and is critical to unpacking the layers of problems with the law creating the Mackinac Straits Corridor Authority that the lame-duck legislature rushed through in late 2018.

“We applaud Attorney General Nessel for clearly recognizing the legislative overreach, restoring the rule of law, and stopping the attack on the Great Lakes and the state constitution, which demands that the state’s air, water, and natural resources are treated and protected as ‘paramount,’” said Liz Kirkwood, an environmental attorney and Executive Director of FLOW (For Love of Water), a Great Lakes law and policy center based in Traverse City.

The attorney general’s opinion on Public Act 359 is binding on state agencies and voids the tunnel agreement called for by the law, and also nullifies the legal effect of the side agreements reached between the state of Michigan under then-Gov. Rick Snyder and Line 5-owner Enbridge. Those agreements allowed continued oil pumping through the Straits, where Lake Michigan meets Lake Huron, and an easement and 99-year lease of Great Lakes public bottomlands to Canadian-based Enbridge for private control of the tunnel for its own gain.

Public Act 359 and the related agreements for a tunnel and continued use of the existing, flawed Line 5 were not authorized under the standards of public trust law; the state and Enbridge flouted the Great Lakes Submerged Lands Act (GLSLA) that requires transfers and agreements for occupancy of the soils of under the Great Lakes by trying to avoid and ignore this most basic law and public trust principles.

Public Act 359 and the side agreements are peppered with other serious problems, most of which are covered by the questions the Governor asked the Attorney General to answer, which include:

  • Adding the tunnel and corridor authority to the 1952 law that created the Mackinac Bridge Authority goes far beyond the original public purpose to build a public bridge;
  • Establishing a term for members of the board of the corridor authority that exceeds the 4-year limit under Article III of the Michigan Constitution;
  • Violating provisions of the state constitution that prohibit fostering private or special purposes, the commingling of the government to aid primarily private projects, the appropriation of public property for private purposes, and the entanglement of the credit and taxpayers of the State for primarily private purposes.

“We hope this critical first step by the Attorney General will be followed by an immediate and full review of the Snyder administration’s and agencies’ deliberate evasion of the rule of law and mishandling of the grave and continuing risks of the existing Line 5, and the real and imminent threat to the Straits of Mackinac, towns and cities like Mackinac Island, tribal fishing interests, private property interests, businesses, and the rights of the public in the soils and waters of the Great Lakes,” said Olson.

FLOW recommends that Gov. Whitmer take immediate action to end the massive threat posed by the existing Line 5 in the Straits of Mackinac in a swift and orderly fashion based on the rule of law under our state constitution, statutes, and the public trust doctrine in the Great Lakes, including by:

  • Acknowledging that State of Michigan agencies are bound by the attorney general’s opinion.
  • Sending a letter to Enbridge indicating that the company should decide for itself, if it wants to build a new oil tunnel, and apply, if it chooses under the Great Lakes to construct a tunnel under the rule of law. The rule of law requires a full consideration of the risk to the paramount public rights in the soils and waters of the Great Lakes, and a showing that the company has no prudent and feasible alternatives to using the Great Lakes as a shortcut for western Canadian oil on its way to refineries in eastern Canada as well as overseas markets. If the company does not chose to do this, or cannot satisfy these mandatory requirements that protect the Great Lakes, then it should choose to use other parts of its several-thousand mile system.
  • Starting the process to decommission the 66-year-old Line 5 pipelines in the Straits of Mackinac, which are operating without lawful authority, in violation of the public trust and GLSLA, and in violation of their 1953 easement granted by the state. If Enbridge chooses to continue operating the existing Line 5 in the future, it can apply under the GLSLA for new authority to continue using Line 5 if it can demonstrate little risk and no feasible and prudent alternative to the unacceptable existing Line 5, but the state is not obligated to agree.

“Public Act 359, coupled with the State’s public entanglement with Enbridge, has put private gain and economic interests above the State’s and public’s paramount trust interest in the waters and soils of the Great Lakes,” said Olson. “The unconstitutional law and entangled state and Enbridge agreements represent one of the largest, if not largest, threats in the state’s history to the state’s ownership and public trust duty to protect the public’s rights and uses from private takeover or harm to the Great Lakes.”


Bypassing, and Now Restoring, the Rule of Law on Line 5

After last year’s election, newly chosen leaders and the old guard with a few weeks left in Lansing rushed in opposite directions. The Snyder administration and legislators intensified their unprecedented, legally questionable attacks on water, the environment, and public health during a lame-duck feeding frenzy.

The new guard, Governor Gretchen Whitmer and Attorney General Dana Nessel, meanwhile formed transition teams and appointed cabinet members, new department heads, and staff to reestablish Michigan’s constitutional mandate that the state shall protect the paramount public concern in the Great Lakes, groundwater, and public health from pollution and harm arising out of water crises like statewide PFAS surface and well water contamination, Detroit drinking water shutoffs, lead and Legionnaire’s Disease in Flint water, and the Enbridge Line 5 oil pipelines in the Straits of Mackinac.

The combination of these crises manifests a far deeper crisis in state government—a breach of trust in the oath of office of state officials to uphold the constitution and rule of law. State leaders under the Snyder Administration and many elected officials deliberately ignored the constitutional and legal mandates and instead chose to serve special private interests.

FLOW’s Commitment: Protecting Public Waters from Pollution and Private Control

Here at FLOW, we are increasing our efforts and projects to protect the paramount public trust concern in water, the environment, and public health through our Campaign for Fresh Water launched last fall. One of these projects is to bring an end to the high risk of extreme damage to the Great Lakes, tribal fishing, drinking water, property, businesses, citizens, and Michigan’s economy from the continued operation of the decaying, 66-year-old Line 5 oil pipelines in the Straits of Mackinac.

FLOW has redoubled our efforts in concert with a large public outcry and movement to decommission or end Line 5, collaborating with Oil & Water Don’t Mix and many local and statewide environmental groups, like National Wildlife Federation and Groundwork Center, individuals, families, businesses, communities, elected officials, and the leadership and legal challenges brought by Michigan’s Indian tribes with treaty rights in the Straits, Straits of Mackinac Alliance, and the City of Mackinac Island.

The former Snyder Administration and state environmental and natural resource agencies, former Attorney General Schuette, and a core of pro-Enbridge legislators in a flurry of agreements, laws, and actions, suspended the state Constitution and rule of law to convey and appropriate public trust lands and waters for Enbridge to build a private oil tunnel for a new Line 5 in the Straits of Mackinac for another 99 years. Worse, these state officials and leaders purported to guarantee Enbridge to keep operating and using Great Lakes bottomlands for its dangerous existing Line 5 for another 10 years—without the required authorization and occupancy or use agreements required by the 1955 Great Lakes Submerged Lands Act (GLSLA) and public trust law that apply to the soils and waters of the Great Lakes.

This is the year of reckoning for Enbridge’s Line 5. It is time to unpack and nullify the unilateral deals made with Enbridge by the Snyder administration and confirmed by the legislature without following the constitution and rule of law.

This is the year of reckoning for Enbridge’s Line 5. It is time to unpack and nullify the unilateral deals made with Enbridge by the Snyder administration and confirmed by the legislature without following the constitution and rule of law. The administration and legislature signed off on a covert deal that would let Enbridge Energy continue pumping 540,000 barrels of oil a day (bbl/day; 1 barrel equals 42 U.S. gallons) through the dual lines laid in 1953 in the Straits and Great Lakes with a catastrophic worse-case damage scenario in the tens of billions of dollars. Unaccountably, the administration and legislature did so despite Great Lakes law in Michigan that prohibits the transfer or occupancy of the state-owned waters and the soils beneath them for private purposes.

Reward for Failure: After Enbridge’s 2010 Kalamazoo Pipeline Disaster, Michigan Officials Doubled Enbridge’s Oil Pumping across Michigan, and then Locked in an Oil Tunnel Deal for 99 Years

How is it that the State ended up rewarding Enbridge for a spill from Line 6B of a million gallons of crude oil and billions of dollars of damage to the Kalamazoo River system? While the State worked with Enbridge to address the damage from its unprecedented 2010 spill, it granted Enbridge a gigantic windfall by incrementally approving, from 2012 to the present, the doubling of Enbridge’s pipeline capacity and oil transport through the Great Lakes. In effect, while Canadians continued to block pipeline projects to transport crude oil to the country’s coasts, and citizens in the U.S. derailed the Keystone XL in the West, the Snyder Administration and former Attorney General Schuette orchestrated a “Great Lakes XL” that is even larger.

And then in 2018, Snyder, in his term’s waning months, and the lame-duck legislature gave away and endangered the Great Lakes to Enbridge, by locking in a 99-year sweetheart deal for Enbridge to build an oil tunnel to convey Line 5 under the Straits and granting Enbridge the cover to keep operating the existing failing Line 5 that threatens tens of billions in damages. On top of this deal, the Administration totally failed to even consider climate change impacts and risks and the rapid shift toward the new renewable energy economy that will leave the state with a billion-dollar dinosaur.

Here’s how the calculated actions of Snyder, Schuette, and their cohorts bypassed legal requirements in seven sweeping steps, along with some advice from FLOW to Michigan’s new leadership at the start of their journey to reestablish the rule of law and rollback the mess:

  1. Bit by Bit, Doubling the Oil Flow on Line 6b after Enbridge’s Kalamazoo River Disaster

First, from approximately 2011 to 2014, the Michigan Public Service Commission (MPSC) approved a series of Enbridge applications to replace short segments, rather than a single application to replace the whole portion, that had the effect of doubling the design capacity of most of Line 6b pipeline from 400,000 to 800,000 barrels (bbl)/day. Allowing the MPSC to review shorter pipeline segments avoided the alternative analysis on the entire Line 6b from Indiana to Sarnia, Canada. 

MPSC rules and decisions, and Michigan’s environmental laws, require a review of likely impacts and alternatives to the entire length of the pipeline. Had this rule been followed, the MPSC would have been required to look at all of the Enbridge lines in Michigan, and determine the overall needs of the public necessity and needs of the company, short and long term, and the alternative or best route or location that would best meet that need with the least impact and risk to water, environment, and communities. That would have included a review of the need for Line 5, including the risks to the Straits of Mackinac and Great Lakes. It also would have required a consideration of the future need for crude oil through Enbridge’s system in Michigan in light of falling crude oil demands caused by the rapid and imminent shift to renewable energy to reduce the effects of climate change.

  1. Increasing Line 5’s Oil Flow in the Straits by 80 Percent

Second, during the same time frame, the MPSC approved the location and installation of new and changed pump stations and anti-friction fluid injection facilities for Line 5, including the Straits segment, so Enbridge could implement its final increment to result in the increase the oil transport capacity of Line 5 from 300,000 to 540,0000 bbl/day.  Again, the MPSC did not evaluate the need, impacts, risks, or alternatives to this overall 80-percent increase in flow volume of crude oil.  Once more, the State allowed Enbridge to avoid the law that required a full evaluation of the purpose.  Had the rule of law been followed in the doubled Line 6B and expanded flow volume in Line 5, the State through proper notice, public input, and evidence would have been required to look at overall impacts, risks, and alternatives and need for the Enbridge system, and Line 5 could have been decommissioned in an orderly manner in exchange for the doubling of Line 6B.

  1. Saddling, Elevating, and Damaging Line 5 in the Straits

Third, although not disclosed by Enbridge until 2016, Enbridge installed saddle supports screwed into the lakebed to support a failing design of Line 5 in the Straits. The original design specified in the 1953 easement and built in the Straits called for the heavy steel dual lines in the Straits segment to be laid on the bottom on the lakebed. If wave action and currents scoured more than 75 feet of soils beneath a segment of the pipes, the company was required to stabilize the line by closing the existence of the spans.

While not disclosed until 15 years later, when filling or grout bags failed, Enbridge in 2001 started installing saddle supports screwed into the lakebed to elevate the heavy dual pipes above the lakebed. Initially, there were 16 supports, more and more were added, and between 2016 and 2018, the Michigan Department of Environmental Quality (DEQ) permitted Enbridge to install more than 70 saddle supports, bringing the total to 200 supports, which has resulted in a suspension of three miles of an aged line above the lakebed.

The DEQ shrouded Enbridge’s failing Line 5 risks and redesign by characterizing the supports as a “repair” and “maintenance.”  This not only covered up the redesign but confined the legally required impact and alternative analysis to a 50-foot radius of lakebed around each support.  As a result, the DEQ ignored and allowed Enbridge to escape the comprehensive review of potential impacts and alternatives to the failing condition of the outdated line required by the Great Lakes Submerged Lands Act.

In addition, Enbridge’s installation of the saddles has damaged Line 5’s anti-corrosion protective coating, a fact that the company hid from Michigan officials for three years during its negotiations to install additional anchor supports.

  1. Signing Side Deals for Another 99 Years of Line 5 in the Straits

Fourth, Governor Snyder, DEQ and the Department of Natural Resources (DNR) signed two agreements with Enbridge between October and the end of December 2018 that purported to transfer state public trust bottomlands and soils of the Straits so Enbridge can build a tunnel for a new 99-year pipeline. The tunnel and new line will take 10 years or more to construct. Until the new line is operating, Enbridge is authorized to continue operating the failing design of the existing aged line.

Under the GLSLA, easements, leases, uses, or improvements on, in, under the state-owned public trust soils of the Great Lakes are prohibited unless authorized within two narrow exceptions: (1) it is for a public purpose, related to navigation, boating, fishing, swimming, or drinking water; and (2) it will not threaten an impairment of the public trust in the waters, soils, or these public trust uses.

Under the GLSLA, easements, leases, uses, or improvements on, in, under the state-owned public trust soils of the Great Lakes are prohibited unless authorized within two narrow exceptions: (1) it is for a public purpose, related to navigation, boating, fishing, swimming, or drinking water; and (2) it will not threaten an impairment of the public trust in the waters, soils, or these public trust uses.  The two agreements that commit leasing, easements, or use of waters and soils beneath the Straits do not require Enbridge to obtain authorization or findings under the GLSLA. In other words, the Governor and his agencies agreed to transfer state public trust lands for the tunnel and the private 99-year new line, and at the same time allow the continued use of public bottomlands for the existing line, without obtaining the authorization required by law.

  1. Ramming through a New Law to Transfer State Public Lands to Canada’s Enbridge without Proper Authorization

Fifth, when the Legislature ram-rodded the passage of Public Act 359 and Governor Snyder signed it into law in late December, they created a corridor authority to sign the tunnel agreement, easements, leases and other commitments for Canadian-based Enbridge to take over the public’s state-owned waters and soils and build the tunnel and its new pipeline. On its face, Act 359 transfers or commits to the authority these state public trust bottomlands without requiring authorization of the conveyance under the GLSLA. Under U.S. Supreme Court and Michigan Supreme Court decisions, any disposition, occupancy, or use must obtain authorization based on findings of no private purpose and no impairment of waters, soils, fishing, navigation or other public rights.  Otherwise, it is prohibited.

  1. Bypassing State Law and Alternatives to Risking the Great Lakes

Sixth, the easement for a public utility, after approval by the MPSC, such as the tunnel or the 99-year lease, or the continued operation of the existing Line 5 in the Straits, must be obtained from the state DNR in addition to the authorization under the Great Lakes Submerged Lands Act. Because the easements involve public trust bottomlands, they cannot be granted unless authorized by the GLSLA or unless based on the standards of the common law of public trust, which requires the comprehensive review of potential impacts and alternatives to the total or substantial change of the outdated dual lines in the soils and open waters of the Great Lakes.  

  1. Appropriating Public Property for Enbridge’s Private Purpose

Seventh, the Michigan Constitution, Art IV, Sec. 30, prohibits the appropriation of public property of the State for private or local purposes. An appropriation occurs where the disposition or transfer of state property, like the public trust waters and soils of the Great Lakes, is granted without findings or full and fair compensation—that is, where the transfer is for free, little consideration, or less than the full public trust value of these waters and soils.

In short, our former Governor, DEQ and DNR Directors, the MPSC, and former Attorney General suspended wholesale the rule of law for the benefit of Enbridge’s massive increase in the volume of crude oil through our Great Lakes State for private gain.

Restoring the Rule of Law and the Paramount Place of the Water and the Great Lakes in Michigan’s Future Prosperity

The first order of business for our new leaders—Governor Whitmer and Attorney General Nessel—is to restore the rule of law on Line 5 in Michigan, and they are off to a good start.  The high risks and more than $6 billion catastrophe from a release of crude oil in the Great Lakes and an estimated additional $45 billion in damage to shipping, steel production, and jobs are unacceptable by any sane measure.  

The public deserves better, the law and state Constitution demand it, and we applaud and urge on the governor and attorney general’s steps to bring Line 5 to a prompt and orderly decommissioning and closure.

Governor Whitmer should direct her new directors of the DEQ and DNR and Attorney General Nessel should direct her lead attorneys on Line 5 and the Great Lakes to conduct a thorough and careful review and reevaluation of the Snyder Administration’s and former Attorney General Schuette’s failure to follow the public trust, GLSLA, and Michigan Constitution in the handling of the entire Enbridge Line 5 controversy.

Buoyed by the work of so many organizations, tribes, communities, individuals and families, and the majority of citizens who elected them, the Governor and Attorney General Nessel and their administrations have a mandate and opportunity to restore water, environment, and public health as paramount in Michigan. The public deserves better, the law and state Constitution demand it, and we applaud and urge on the governor and attorney general’s steps to bring Line 5 to a prompt and orderly decommissioning and closure. 

Jim Olson, President and Founder

Enbridge has alternatives within its pipeline system to meet all of its and Michigan’s needs without using the Straits and the Great Lakes.  There are several good solutions to assure continued delivery of propane to rural areas in the Upper Peninsula. It may even save Enbridge and its shareholders from shouldering a future stranded asset, as the need for Alberta crude oil, including through Line 5, will plummet in the next decade with the rise of the new renewable energy economy backed by public demand.


FLOW Supports Gov. Whitmer’s Request for a ‘Line 5’ Opinion from Attorney General


FOR IMMEDIATE RELEASE:                                                                                         January 2, 2019

Jim Olson, Founder and President                                                             Email: olson@envlaw.com
FLOW (For Love of Water), Traverse City, MI                                         Web: www.FLOWforWater.org
Cell: (231) 499-8831; Office: (231) 944-1568


FLOW Supports Gov. Whitmer’s Request for an Opinion from Attorney General on Legality of Hastily Crafted Law and Side Agreements on ‘Line 5’ Oil Pipelines and Proposed Tunnel in Mackinac Straits


The following statement can be attributed to Jim Olson, environmental attorney, founder, and president of FLOW (For Love of Water), a Great Lakes law and policy center based in Traverse City:

“This first and immediate step by Gov. Gretchen Whitmer in a letter asking Attorney General Dana Nessel for an opinion on Public Act 359 is critical in unpacking the layers of problems with the newly enacted law, any tunnel agreement, and most importantly the massive threat posed by the existing Line 5 in the Straits of Mackinac, a threat that must be ended in a swift and orderly fashion based on the rule of law under our state constitution, statutes, and the public trust doctrine in the Great Lakes.”

“In the last three weeks of 2018, then-Gov. Rick Snyder, the Department of Environmental Quality, and Department of Natural Resources signed agreements to enable Enbridge to construct a tunnel that the state would own and lease to Enbridge for 99 years for a new crude oil pipeline under the waters and in the soils of the bottomlands of the Straits of Mackinac. In order to finalize the deal before the end of the year, the Republican-controlled legislature during the lame-duck session rushed through a law—Public Act 359—that set up a Mackinac Straits Corridor Authority to sign the tunnel deal with Enbridge and guarantee the transfer of publicly owned and controlled Great Lakes bottomlands and other financial benefits to Enbridge for private gain, the 99-year privately owned pipeline.

“During this same time, Governor Snyder, the DEQ, DNR, and Enbridge without public review finalized a separate agreement that would give Enbridge the right to continue using its existing dangerous and flawed Line 5 pipelines in the open waters of the Mackinac Straits for another 10 years, or as long as it takes to complete the tunnel and install the new pipeline.

“Everyone agrees that the release of oil to the Great Lakes would cause massive harm to those waters, as well as businesses, communities, property owners, tribal fishing rights, and the public’s paramount rights for fishing, boating, and recreation protected by the public trust doctrine – an ancient principle that prohibits the transfer of public lands and waters without compliance with laws that assure a public purpose and no imprudent risks to health, environment, and property.

“Public Act 359, coupled with the State’s public entanglement with Enbridge, puts private gain and economic interests above the State’s and public’s paramount trust interest in the waters and soils of the Great Lakes.  The law and entangled state and Enbridge agreements represent one of the largest, if not largest, threats in the state’s history to the state’s ownership and public trust duty to protect the public’s rights and uses from private takeover or harm to the Great Lakes. Act 359 and these agreements for a tunnel and continued use of the existing, flawed Line 5 were not authorized under the standards of public trust law; the state and Enbridge flouted the Great Lakes Submerged Lands Act that requires transfers and agreements for occupancy of the soils of under the Great Lakes by trying to avoid and ignore this most basic law and public trust principles.

“Public Act 359 and the agreements are peppered with other serious problems, most of which are covered by the questions the Governor has asked the Attorney General to answer.  These include:

  • Adding the tunnel and corridor authority to the 1952 law that created the Mackinac Bridge Authority goes far beyond the original public purpose to build a public bridge;
  • Establishing a term for members of the board of the corridor authority that exceeds the 4-year limit under Article III of the Michigan Constitution;
  • Violating provisions of the state constitution that prohibit fostering private or special purposes, the comingling of the government to aid primarily private projects, the appropriation of public property for private purposes, and the entanglement of the credit and taxpayers of the State for primarily private purposes.

“We hope this critical first step by the Governor and Attorney General will be followed by an immediate and full review of the Snyder administration’s and agencies’ mishandling of the grave and continuing risks of the existing Line 5, and the real and imminent threat to the Mackinac Straits, towns and cities like Mackinac Island, tribal fishing interests, private property interests, businesses, and the rights of the public in the Great Lakes.”


State should end discussion, take action on Line 5


When the police pulls a resident over for going 100 mph in a 55-mph zone, they don't cluck their tongues -- they click their ticket books.

But when Michigan’s state government catches Enbridge Energy putting the Great Lakes at risk by failing again to disclose dangerous conditions on its Line 5 oil pipelines in the Mackinac Straits, the response is paralysis. The state has again caught Enbridge ignoring its legal obligation to be a proper steward of the submerged land that the state allows the company to occupy with its pipeline.

But all we're hearing out of Lansing, and particularly Attorney General Bill Schuette is an expression of disappointment.

The difference between strict enforcement of laws against individuals and giving an oil transport giant chance after chance to meet its fundamental responsibility not to harm public waters is as stark as the difference between a single speeding motorist and a catastrophic oil spill fouling the drinking water source for millions.

The accumulation of studies, evidence of pipeline delamination and bends in June, and now exposed metal with likely corrosion, signals a dangerously flawed and ultimately incurable pair of sunken pipelines.

It’s time for our state government to stop treating the 1963 Constitution, statutes, and common law that protect our lakes as nice but meaningless environmental policy statements and start treating them as the duty the people through the Constitution and our courts have mandated. More than ever, it’s time to shut down Line 5.


FLOW's senior advisor, Dave Dempsey, has 35 years experience in environmental policy. He served as environmental advisor to former Michigan Governor James Blanchard and as policy advisor on the staff of the International Joint Commission.  He has also provided policy support to the Michigan Environmental Council and Clean Water Action.  He has authored several books on the Great Lakes and water protection.


Opinion on Aquaculture by Bill Schuette, Attorney General

Great Lakes advocates say that commercial net-pen fish farming, pictured above, does not belong in Michigan’s public waters.
Since our A.G. has emphasized the importance of public trust in the Great Lakes and navigable lakes and streams, including Great Lakes, we’ve analyzed the doctrine, applied it to fish farming in Great Lakes, and the answer is: it cannot be authorized under the public trust doctrine, not even by legislative amendment to expand the definition of aquaculture as implied by the A.G.’s opinion.

 

Read the recent Attorney General opinion on Aquaculture in the Great Lakes: Click here! 

Read More about Aquaculture in FLOW’s recent Aquaculture issue brief! 

(Also available in Flipbook form)

 

Officials require more supports beneath oil pipes

Click here to read the article on record-eagle.com 

By The Associated Press

July 25, 2014

TRAVERSE CITY, Mich. (AP) — Two oil pipelines at the bottom the waterway linking Lakes Huron and Michigan will get additional support structures to help prevent potentially devastating spills, officials said Thursday.

Michigan Attorney General Bill Schuette and Dan Wyant, director of the Department of Environmental Quality, said they had put Enbridge Energy Partners LP on notice following the company’s acknowledgement it was partly out of compliance with an agreement dating to 1953, when the pipelines were laid in the Straits of Mackinac.

As a condition of an easement granted by the state, Enbridge agreed that support anchors would be placed at least every 75 feet. In a response last month to a lengthy series of questions about the condition of the lines from Schuette and Wyant, the Canadian company acknowledged some sections don’t meet the requirement, although the average distance between supports is 54 feet.

“We will insist that Enbridge fully comply with the conditions of the Straits Pipeline Easement to protect our precious environmental and economic resources and limit the risk of disaster threatening our waters,” Schuette said.

Enbridge spokeswoman Terri Larson said the company had agreed to add more supports, even though engineering analyses peer-reviewed by experts at Columbia University and the University of Michigan concluded previously that gaps of up to 140 feet between supports would be safe. The work will begin in early August and be completed within 90 days, she said. Afterward, the average distance between supports will be 50 feet.

“The Straits of Mackinac crossing has been incident-free since it was constructed in 1953,” Larson said. “Through even greater oversight, the use of new technology and ensuring all risks are monitored and where necessary mitigated, Enbridge is committed to maintaining this incident-free record into the future.”

The two pipelines are part of the 1,900-mile Lakehead network, which originates in North Dakota near the Canadian border. A segment known as Line 5 runs through northern Wisconsin and Michigan’s Upper Peninsula before ducking beneath the Straits of Mackinac, then continuing to Sarnia, Ontario.

The line divides into two 20-inch pipes beneath the straits at depths reaching 270 feet and carries nearly 23 million gallons of crude oil daily. The 5-mile-wide straits area is ecologically sensitive and a major tourist draw.

A June report by hydrodynamics specialist David Schwab of the University of Michigan Water Center concluded that because of strong currents, a rupture of the pipeline would quickly foul shorelines miles away in Lakes Huron and Michigan.

Larson said Enbridge began installing steel anchors for the underwater lines in 2002, replacing sandbag supports. They consist of 10-foot-long screws augured into the lakebed on either side of the pipes, holding a steel saddle that provides support. No washouts have been seen during inspections since then, she said.

Schuette and Wyant said their staffs are still reviewing Enbridge’s responses to other questions about the pipelines.

Enbridge Energy Partners is a unit of Calgary, Alberta-based Enbridge Inc.

DEQ and Attorney General Determine Enbridge in Violation of 1953 Easement

On July 1st, FLOW along with 16 conservation, water and environmental groups and the Little Traverse Bay Bands of Odawa Indians sent a letter to Michigan Governor Rick Snyder urging greater state action to regulate Enbridge’s 61 year-old Line 5, which transports some 23 million gallons of crude oil and other petroleum products under the Straits of Mackinac each day. This means that at any given moment, 365 days a year, nearly one million gallons of crude oil is flowing under the Straits. The letter pointed out potential violations in operations and public disclosure requirements established by Public Act 10 of 1953 and the Great Lakes Submerged Lands Act. Read the press release here. 

The Department of Environmental Quality (DEQ) and the Attorney General have since determined, in a July 24, 2014 letter, that the company is in violation of the 1953 easement’s spacing requirement for pipeline supports. In response, the DEQ issued Enbridge a Great Lakes Submerged Lands Act (GLSLA) permit for maintenance and structural improvements on the same day (Enbridge’s final permit No. is 14-49-0017-P). Read the official letter here.

Although this is a step in the right direction, FLOW and other groups continue to urge the Governor and the DEQ to require an occupancy agreement for the entire pipeline under the Straits of Mackinac.

A State analysis of reasonable and proper pipeline procedures is necessary given modern technology, industry standards, products being transported, and risks to our public resources. Requiring Enbridge file a GLSLA occupancy agreement would allow this analysis and fulfill this term of the easement. As trustee of the Great Lakes, Governor Snyder has the authority under the 1953 easement, Act 10 of 1953, and the common law of public trust to demand that Enbridge file such an agreement.

FLOW and the other coalition groups from the July 1st sign-on letter are planning to meet with Governor Rick Snyder’s office and the DEQ later this month to discuss the State’s vital role in regulating the Line 5 pipeline and protecting these public trust waters of the Great Lakes.